Preliminary Plans for Interconnect Pipeline Complete
Construction to Begin in 2009
by Lane Roberts

Preliminary plans for the 8.5 mile “Centennial to Castle Rock Interconnect Pipeline Project” have been completed.

The 30-inch pipeline will run from storage tanks on Griggs Road through Castle Pines North (CPN) along the Xcel power line corridor, and will end at a water storage facility in Castle Rock. The Castle Pines North Metro District, the Town of Castle Rock, and the Centennial Water and Sanitation District are working together on the project.

The preliminary plans included establishing size and alignment of the pipeline, developing hydraulic profiles, and determining metering points, value locations and pump stations, along with a cost analysis.

According to Metro District Manager James McGrady, the next step is to finalize an agreement with Centennial Water and Sanitation to convey reusable water from CPN and Castle Rock back to the respective service areas.

“A hydraulic model of Centennial’s water system was developed to determine what improvements are needed within Centennial’s water distribution system in order to convey water from their water treatment plant to the tank located on Griggs Road,” stated McGrady.

McGrady said cost sharing agreements between the District and Castle Rock are still being negotiated.

Once agreements are in place, final design of the pipeline will begin. Construction for the pipeline could begin in early 2009.

Home | News | Area News
Area News
  Home Page for the CPNHOA web siteDirectory of contacts for the CPN communitySite Overview  
Back to Top

OUR COMMUNITY . . . .   Calendar Churches & Synagogues Development Events Kids Maps Recreation Parks Trails & Open Space Safety Schools Scouts Sports and Recreation Volunteers
FEATURES . . . . . . . . . Album Feature Stories Gardening Golfing Pets Spotlight Wildlife
ORGANIZATIONS . . . . Master Association Neighborhood HOAs Metro District Parks Authority County
NEWS & ISSUES . . . . . Quick News 2008 News Archives 2007 2006 2005 2004 2003 2002
CONTACTS & SERVICES Covenants Email Alerts Landsape Maintenance Newsletter New to CPN Snow Removal Telecom Website
MARKET PLACE . . . . . . Business Directory Business News Business Partners Classifieds Restaurants Submittal Form Swap Who to Hire

Castle Pines North Master Association

Telephone and fax:      303-482-3078
Email:                         admin@cpnhoa.org
Website:                     www.cpnhoa.org

Mailing Address:          CPN Master Association
                                  7402 Yorkshire Drive
                                  Castle Rock, CO 80108

NOTE:  The Master Association has an office location.  We have an independent team of part-time contractors. All inquiries to the Master Association are responded to as soon as possible.
  The CPN website is developed and maintained by the CPN Master Association. 

The Master Association provides neighborhood HOAs with free, customized web pages, complete with detailed information exclusive to each HOA. 

To submit updates or comments, please contact the CPN Webmaster

Website Information


Copyright © 1999-2008 Castle Pines North Homeowners Association All rights reserved.